The technical and financial pland were fully prepared for project implementation from the end of 2019, however, due to the COVID-19 pandemic, until October 28th, 2020 was the groundbreaking ceremony held at the plant, with an initial capacity of 0.9 MWh. On December 22nd, 2020, the solar power project at Song Duong Surface Water Plant were officially connected to the national grid.
The participants in the project implementation:
Investor: AquaOne Water Joint Stock Company
Main contractor: Aone Vietnam Company Limited
Solar power consulting and design company: IBC solar, Germany